Fifteen Minutes: Mem Hall Makeover

Cost: Four million Katherine B. Loker dollars. Height: 140 feet Start: June, right after commencement Finish: December Materials: Steel frame,
By V.c. Hallett

Cost: Four million Katherine B. Loker dollars.

Height: 140 feet

Start: June, right after commencement

Finish: December

Materials: Steel frame, fire resistant plywood and fire protection system (the original tower burned down in a 1956 blaze), polychrome slate (fading green, red and black), copper finials and the piece de la resistance of four corner brick and stone precipices.

Architect: CBT (Boston)

Tags