News
Garber Announces Advisory Committee for Harvard Law School Dean Search
News
First Harvard Prize Book in Kosovo Established by Harvard Alumni
News
Ryan Murdock ’25 Remembered as Dedicated Advocate and Caring Friend
News
Harvard Faculty Appeal Temporary Suspensions From Widener Library
News
Man Who Managed Clients for High-End Cambridge Brothel Network Pleads Guilty
Construction work began on Mt. Auburn St. yesterday morning, as the city continued the latest phase of its massive sewer remodeling project.
And the work on DeWolfe St. that had taken much of the summer was "essentially completed" Friday, according to project coordinator Brian C. Culver, allowing the street to be reopened to traffic.
The Mt. Auburn St. project, however, will not stop as much traffic as work on DeWolfe St. did--one lane of traffic will remain open on Mt. Auburn St. until the project is completed sometime late next month, Culver said.
Also yesterday, Holyoke Place--the short street off Mt. Auburn St. leading up to Lowell House--was closed for two weeks for sewer renovation.
The castle of the Harvard Lampoon--a semi-secret Bow St. social organization that rarely publishes a so-called humor magazine--seems to be a focal point of the latest renovations.
Over the past two months, more and more large cement pipes have sprung up around the sides of the building. Nearby on Bow St. on the side of St. Paul'sCatholic Church, dirt and bulldozers have markedthe site of even more work for more than a weeknow. Yellow ribbons labeled "caution" warnedpedestrians not to cross Mt. Auburn St.yesterday--making visits to Tommy's House of Pizzaand Sage Jr.'s slightly more inconvenient. By the end of the summer, Plympton St. and MillSt. will also see renovations. But all the major sewer renovations below theUniversity's streets will be done in time for fallregistration, Culver said in an interview Friday. The latest ren@[ions are part of the finalphase of a 25-year Cambridge sewer renovationproject that will involve all of the Square by thetime the completion date arrives. In this sixth phase of the project, which wasinitiated in October 1993, workers will constructthe main trunk of a storm sewer from the CharlesRiver up DeWolfe St. The trunk will be extended beyond Quincy Squareup Quincy St. to Kirkland St. and Memorial Hall,Culver said. The present work is just one of three contractsin phase six of the project. The contractor forecasts completion of theproject by March, 1995, Culver said, and theproject is presently more than 50 percent done. But the contract will be "essentiallycompleted"--i.e., all work excepting minorrepairs--by the fall of this year. Contracts have not been awarded for the secondand third components of the phase. The second component, which Culver labelled'1b,' is an extension of the line on DeWolfe St.through Quincy Square and up to the Fogg ArtMuseum. The third component, '1c,' is the extension ofa smaller portion of the pipe to the east ofQuincy Square, Culver said. The work on Mt. Auburn St. involves theinstallation of a line from the trunk down toDunster St. It was necessary to close DeWolfe St. for thework, Culver said, because the main trunk isunusually large--the pipe has an interior diameterof six feet and an exterior diameter of eightfeet. DeWolfe residents expressed some unhappinesswith the project's noise and odor as well as itsinconvenience during the school year. But on streets above branches to the main line,he added, some amount of traffic is permissible. "It does take up most of the street to buildit," the coordinator said of the main trunk. "But on the side streets, it doesn'tnecessarily stop the street," he added. And at night, Culver said, many of the trenchescan be covered, restoring full access to thestreets for both pedestrians and automobiles. The project will ultimately be completed in theyear 2000, and will cost the city in excess of $20million.
Nearby on Bow St. on the side of St. Paul'sCatholic Church, dirt and bulldozers have markedthe site of even more work for more than a weeknow.
Yellow ribbons labeled "caution" warnedpedestrians not to cross Mt. Auburn St.yesterday--making visits to Tommy's House of Pizzaand Sage Jr.'s slightly more inconvenient.
By the end of the summer, Plympton St. and MillSt. will also see renovations.
But all the major sewer renovations below theUniversity's streets will be done in time for fallregistration, Culver said in an interview Friday.
The latest ren@[ions are part of the finalphase of a 25-year Cambridge sewer renovationproject that will involve all of the Square by thetime the completion date arrives.
In this sixth phase of the project, which wasinitiated in October 1993, workers will constructthe main trunk of a storm sewer from the CharlesRiver up DeWolfe St.
The trunk will be extended beyond Quincy Squareup Quincy St. to Kirkland St. and Memorial Hall,Culver said.
The present work is just one of three contractsin phase six of the project.
The contractor forecasts completion of theproject by March, 1995, Culver said, and theproject is presently more than 50 percent done.
But the contract will be "essentiallycompleted"--i.e., all work excepting minorrepairs--by the fall of this year.
Contracts have not been awarded for the secondand third components of the phase.
The second component, which Culver labelled'1b,' is an extension of the line on DeWolfe St.through Quincy Square and up to the Fogg ArtMuseum.
The third component, '1c,' is the extension ofa smaller portion of the pipe to the east ofQuincy Square, Culver said.
The work on Mt. Auburn St. involves theinstallation of a line from the trunk down toDunster St.
It was necessary to close DeWolfe St. for thework, Culver said, because the main trunk isunusually large--the pipe has an interior diameterof six feet and an exterior diameter of eightfeet.
DeWolfe residents expressed some unhappinesswith the project's noise and odor as well as itsinconvenience during the school year.
But on streets above branches to the main line,he added, some amount of traffic is permissible.
"It does take up most of the street to buildit," the coordinator said of the main trunk.
"But on the side streets, it doesn'tnecessarily stop the street," he added.
And at night, Culver said, many of the trenchescan be covered, restoring full access to thestreets for both pedestrians and automobiles.
The project will ultimately be completed in theyear 2000, and will cost the city in excess of $20million.
Want to keep up with breaking news? Subscribe to our email newsletter.