Weld Boathouse Nearing Completion

NO WRITER ATTRIBUTED

Work has progressed on the new Weld boathouse so rapidly that it is expected that by April 1 the whole of the inside will be complete. The laying of the granolithic floors has just begun and, weather permitting, they will be finished in 10 days. After the floors are ready the lockers will be installed.

Work on the outside of the building has been hindered by the frost, so that the plastering of the outside walls has not yet been started.