Owing to the present favorable weather conditions the work on the new Weld boathouse is progressing rapidly, and at present 75 men are working to complete the roof before the next cold weather. Practically all the steel work is finished. On the water or south side, both the upper and lower balconies are completed and nothing remains to be done except to give the brick a final dressing after the exterior work of the entire building is finished. All the cement is laid for the terrace on the north side.